AVAILABLE NOWPods
What you can buy today is a pod, underground, on your own site
A Goliath pod is a mini AI data centre we build, install, own, operate and maintain below grade on your premises. It starts at 50 PB of usable storage and 72 Blackwell Ultra accelerators, from $15M. Your data, your site, our leased solution. Continental United States only.
50 PBUsable storage, base pod
72Accelerators, base pod
$15MFrom
48 statesContinental US only
What it is
Your data, your site, our leased solution
Beta access to the hosted system is closed at 930 companies. The pod programme is open, and it is the only thing a company can buy from us today.
A pod is a complete AI data centre in three precast vessels, installed below grade on land you control. Compute in one vessel, storage in the second, power and plant in the third. We design it against your parcel, we obtain the permits, we excavate, we install, we commission, and from that point we operate it. You do not rack anything, patch anything, cool anything or page anyone at three in the morning.
The split is deliberate. The data is yours and never leaves your premises unless you send it. The site is yours, and so is the dirt above the pod. The hardware is ours, the operation is ours, and the liability for keeping it correct is ours. That is the whole reason this exists: companies with data that cannot leave a building still need a frontier fleet working against it, and shipping the data to a region is not an option for them.
Everything here is indicative until a site survey. Every figure on this page is either confirmed or withdrawn in writing after the survey, before anything is signed.
Base pod, as delivered
72 x NVIDIA B300 Blackwell Ultra (one GB300 NVL72 rack)NVIDIA Vera Rubin VR200 NVL144 available in place of B300 on requestNVIDIA BlueField-4 CMX for the GPU context tierNVIDIA Quantum-X800 InfiniBand XDR inside the pod50 PB usable storage across four tiers1.6 MW installed electrical capacity, 1.25 MW at steady state5 MWh LFP battery, separate vessel, NFPA 855 clearances2 x 1.5 MW Tier 4 Final generators, N+1, 72 hours at full loadDirect to chip liquid cooling to a buried ground loop, no evaporative waterDual diverse fibre, 2 x 400G to your core, out of band on a separate pathThree precast vessels, installed 6 to 12 m below grade
Storage, same four tiers as the main hall
Tier 1 · 1 PB · NVIDIA STX with BlueField-4 CMX · KV cache, inference context, live checkpointsTier 2 · 4 PB · VAST Data all flash NVMe · training sets, model repository, parallel accessTier 3 · 45 PB · MinIO AIStor ExaPOD on enterprise HDD · bulk data, video, documents, embeddings, archiveTier 4 · immutable DR replica held off site in our vault, or on a second pod you ownOne namespace, policy driven promotion between tiers 2 and 3Checksum on ingest and on every read, erasure coded capacity tiers
Capability
What a pod can actually do
A pod runs the same stack as the main hall, at a smaller scale and against your estate instead of ours. The Cortex schedules locally, the Slings work locally, and Cerebrum adjudicates locally, which means the guardrail is inside the building with the data rather than across a network boundary from it.
The difference that matters operationally is egress. A pod can be configured so that no byte of your data has a path out, including to us. Our monitoring runs over telemetry and health metrics on a separate channel that carries no customer payload, and that channel is auditable by you at any time.
What it runs
Goliath Cortex scheduling locally against your estateUp to 60 concurrent Slings on the base podCerebrum and the AEGIS release interlock, in the podFine tuning on your data, with the resulting weights held in the podInference at single digit milliseconds to equipment on your floorSynthesised adapters against your systems, no connector library, no SaaS hopRetrieval and embedding over your document, video and sensor estateAir gapped operation with a scheduled sync window, or no sync at allBurst to the main hall when you permit it, hard blocked when you do notProvenance chain written locally and sealed into the immutable DR copyTwo key release, short lived credentials, dead man interlock on every Sling
What it is for
Data that is not allowed to leave the premisesRegulated estates: HIPAA, CJIS, CUI under NIST 800-171, PCI, ITAR with a TAA in placeSites where the sensor and video volume makes egress the dominant costIndustrial and process floors needing deterministic local latencyClassified adjacent work where a hosted region is not an optionCompanies whose counsel will not sign a cloud data processing agreementContinuity of operations when the site loses its external link entirely
Site qualification
Most parcels do not qualify, and we say so early
A pod goes underground, which means the parcel decides the project. We survey before we quote, and we withdraw rather than compromise on any item below. These are not preferences. A pod that is sited wrong is a pod that floods, shifts, overheats or cannot be legally occupied, and all four of those are our problem for the length of the lease.
Two items disqualify more sites than everything else combined: a mapped active fault inside the exclusion distance, and a groundwater table above the vessel invert. Neither can be engineered around at this price.
Ground and geology
No mapped active fault within 2 km, no state designated earthquake fault zone on the parcelSeismic site class A through D, no liquefaction susceptible soilsGroundwater table below the vessel invert, confirmed by boringNo karst, no mine workings, no undocumented fill, no landfill or brownfield historySlope under 8% across the working areaOutside the FEMA 100 year floodplain, no mapped Zone A or Zone VRadon mitigation designed in where the EPA zone requires itGeotechnical report with a minimum of three borings to 1.5 times vessel depth
Utilities and plant
3 phase utility service with 2.5 MVA available, confirmed by a utility capacity letterWater access for makeup, standpipe and fire service, 500 gpm at 20 psi within 300 ftGenerator location for 2 x 1.5 MW with a 10,000 gallon double wall fuel tankRoom for the battery vessel at NFPA 855 separation from occupied structuresTwo diverse fibre entrances, or a path we can build to two811 one call clearance and a private utility locate across the full footprint
Access and land control
Minimum 0.4 acre clear working area during installationCrane access with 14 ft overhead clearance to the set locationLegal truck route for a 40 ft vessel on a lowboyRecorded easement over the pod footprint and the access path for the lease termSubsurface rights confirmed, no conflicting mineral or oil and gas leaseLender consent where the parcel is encumberedContinental United States only: no Alaska, no Hawaii, no territories, no export
Legal and permitting
The approvals we obtain, and the rules we both live inside
We run the permitting. You sign as the property owner where the jurisdiction requires it, and you give us the site control to do the rest. The list below is the category list rather than a promise about any one address, because requirements move between a county and the county next to it. Nothing here is represented as already granted at your site.
Two categories are worth reading before you call. Export control governs the accelerators themselves, which means a non-US person cannot be given access to the pod interior or to the console without the appropriate authorisation, and that constraint binds you as well as us. And the pod is an occupiable underground structure, which brings life safety requirements that are stricter and less negotiable than anything in a surface building.
Land use and construction
Zoning approval or conditional use permit for a subsurface accessory structureBuilding permit under the locally adopted IBC, including Section 405 underground building provisionsExcavation, shoring and grading permitsOSHA 29 CFR 1926 Subpart P compliance for the excavation phaseLife safety: two means of egress, smoke control, standpipe, emergency lightingFire marshal approval of the battery vessel under NFPA 855 with UL 9540 and 9540A listingsElectrical permit and utility interconnection agreement, NFPA 70 and 70ELocal fire code review under the adopted IFC for the fuel and battery occupancies
Environmental
EPA NPDES construction general permit and a SWPPP for land disturbance of one acre or moreClean Water Act Section 404 permit from the Corps of Engineers if waters or wetlands are touchedNEPA review where there is a federal funding, land or permit nexusState air permit for the standby generators, EPA NSPS Subpart IIII and RICE NESHAP Subpart ZZZZSPCC plan under 40 CFR 112 for the fuel tank, with secondary containmentState water withdrawal or water rights authorisation where makeup water is drawn on siteSection 106 historic and tribal consultation where triggered by the ground disturbanceEndangered Species Act consultation where a listed species or critical habitat is present
Export control, sanctions and data
EAR controls on advanced computing hardware, including ECCN 3A090 and 4A090 classificationNo re-export, no transfer and no relocation of the pod or any component out of the United StatesDeemed export rules: no foreign national access to the pod interior or console without authorisationOFAC sanctions screening of the site, the entity and the personnel with accessCFIUS review where the customer has foreign ownership, control or influenceHIPAA business associate agreement where protected health information is processedCJIS security addendum and personnel screening where criminal justice information is processedNIST SP 800-171 and CMMC alignment where controlled unclassified information is processedITAR registration and a technical assistance agreement where defense articles or data are in scopeState data breach notification statutes, and state privacy acts where resident data is processed
Commercial terms
Pods are leased, not sold. Title stays with Goliath SI for the full termA pod remains on the installed site. It is never relocated, sublet, assigned or removed by the customerUCC-1 filing against the equipment, and a recorded memorandum of the site agreementRight of entry for inspection, maintenance, audit and incident response, announced or unannouncedContinuous remote monitoring of health, power, thermal, tamper and custody stateImmediate suspension and secure wipe rights on an export, sanctions or tamper findingDecommissioning at end of term is ours: crypto erase, extraction, restoration of the site36 month minimum term, renewal priced at renewal
Operations
We manage it, we monitor it, and we will inspect it
The pod is operated from the main hall. Scheduling, patching, firmware, model updates, capacity planning, failure prediction and replacement all happen on our side of the line, and the customer sees the fleet rather than the plumbing.
Inspection is not a formality and it is not negotiable. We reserve the right to enter the site and the pod for inspection, maintenance, audit, custody verification and incident response, with notice or without it, and we exercise that right on a schedule plus whenever telemetry says we should. Tamper seals on the compute vessel are checked physically, not remotely. A pod whose interior has been opened by anyone outside our operations team is suspended on discovery, and that is a contract term rather than an escalation path.
The reason is the same reason the main hall is underground and unnamed. These are controlled accelerators holding regulated data under a custody chain that has to stand up in an audit years later. A custody chain nobody physically verifies is a story, not a chain.
Included for the term
24/7 monitoring and incident response from the main hallAll maintenance, parts, firmware and software updatesTwo scheduled on site visits per quarter, plus unannounced inspectionFour hour parts dispatch anywhere in the continental United StatesAccelerator and drive replacement on failure prediction, before failureHardware refresh at the generation boundary within the termQuarterly custody and provenance audit, with the record handed to youCapacity and growth review against your own data growth rate
What stays with the customer
The data, and the decision about whether any of it leavesThe land, the easement and the site servicesPhysical perimeter security outside the vesselsUtility and fuel accounts, and the power billYour own users, policies and what you point the fleet at
Pricing
From $15M. A doubling of capacity is a doubling of price
The base pod is 50 PB usable and 72 accelerators, from $15M. Capacity scales by doubling, and the price doubles with it, because at this scale the cost is the hardware and the hardware does not get cheaper by the pallet.
The figure covers design, permitting, excavation, installation, commissioning, the hardware, the full operating and maintenance term, monitoring, parts, refresh at the generation boundary, and decommissioning at the end. It does not cover your utility connection work, your power and fuel consumption, or site works outside the pod footprint, and we quote those separately once the survey tells us what they are.
Pods can be stacked on one site. Two base pods on the same parcel share the ground loop and the generator plant, which is the one place where the ladder bends in your favour, and the survey will say by how much.
The ladder
50 PB · 72 accelerators · from $15M100 PB · 144 accelerators · from $30M200 PB · 288 accelerators · from $60M400 PB · 576 accelerators · from $120M800 PB · 1,152 accelerators · from $240MAbove 800 PB the configuration is designed rather than selected
Included in the figure
Site survey, geotechnical investigation and designPermitting, agency coordination and the approvals we holdExcavation, shoring, vessel set and site restorationAll hardware: accelerators, fabric, all four storage tiers, plant, battery, generatorsCommissioning and acceptance testing against the regression suiteFull operating term: management, maintenance, parts, monitoring, inspectionGeneration boundary hardware refreshCrypto erase, extraction and site restoration at end of term
Quoted separately after survey
Utility service upgrade and interconnection workPower and generator fuel consumptionFibre construction beyond the parcel boundarySite works outside the pod footprint, access roads, perimeter securityAdditional DR replicas beyond the included immutable copy
Process
From first call to accepted pod
The order below is not flexible. The survey comes before the quote, the permits come before the excavation, and the acceptance test comes before you put a single workload on it. Every step we have ever been asked to run out of order is a step that cost the customer more than waiting would have.
Sequence
1 · Parcel screen against the disqualifying criteria, no charge, days2 · Site survey, borings, utility capacity letter, fibre path check3 · Confirmed quote, or a written withdrawal with the reason4 · Agreement, easement recording, lender consent, export and sanctions screening5 · Design and permitting6 · Excavation, vessel set, plant and utility tie in7 · Commissioning, regression suite, custody chain established8 · Acceptance, then the operating term begins